Project MCG-2041
Atelier

Project MCG-2041

MCG-2041 · Millwork Package · Novak Millworks Scope
Active
Project Status
On TrackIn Progress
Sync Calendar
38%
InquiryMar 2026
Contract
SignedMay 2026
Shop Drawings
+ SamplingNow
In
ProductionAug 2026
Production
CompleteOct 2026
QA
ReviewNov 2026
Pre-Ship
& CratingNov 2026
ShippedNov 2026
Delivered
to SiteDec 2026
Timeline set by the Atelier team (read-only) · Next milestone: Shop drawing approvals — Aug 9, 2026 · Questions? Message the Atelier team
Needs Action 2 shop drawings came back with revision requests — KCHN-05 Rev C due Aug 8 · WRD-01 notes posted by the Atelier team. Open Drawing Queue

Production Items 28 items in your scope · 12 in production · 3 in QA All 28 →

⌕ Search by name or plan code…
STATUS All ▾ DRAWINGS All ▾
Cut List CSV ListCards
KCHN-05
KCHN-05 · Millwork · Qty 1 · 194.5 × 112 × 108 in · Rev C revision due Aug 8
68%
BR-01
BR-01 · Millwork · Qty 1 · 117 × 33 × 132 in
72%
WRD-01
WRD-01 · Millwork · Qty 1 · 274 × 174 × 132 in · Drawing approved — release to floor
66%
KCHN-01
KCHN-01 · Millwork · Qty 1 · 132 × 48 × 36 in · In production
45%
CBT-03
CBT-03 · Millwork · Qty 1 · 130.5 × 71.5 × 120.75 in · Awaiting drawing approval
12%
Showing 5 of 28 items · Open the full register →
Shop Drawing Queue Planned — consolidated register 4
KCHN-05 Rev C — revision requested, due back Aug 8
CBT-03 Rev A — submitted Jul 30, with Atelier for review
LNDR-01 Rev A — submitted Jul 28, with Atelier for review
SNK-07 Rev B — approved Aug 1 · released to production
Open drawing queue →
Upcoming Ship Dates
Shipment MCG-2041-S01 — crate by Nov 5 · ship Nov 12 (dining + kitchen millwork)
Shipment MCG-2041-S02 — crate by Nov 24 · ship Dec 1 (wardrobes + baths)
Delivery routing and site address are released by the Atelier team with the dispatch pack.
Open shipping & crating →
Messages 2
“Rev C markups posted for the Dirty Kitchen…”
Atelier Team — Daniel Reyes (PM) · 2 days ago — please confirm the revised toe-kick detail before resubmitting.
Open messages →
QA / Photos Planned
3 items due for in-progress QA photo sets this week · 96% first-pass QA rate on submitted sets.
Upload QA photos →

Documents All Documents →

Recent Activity

AT
SNK-07 Rev B shop drawing approved by the Atelier team — released to production.
Atelier Team · 1 day ago
Approved
TN
Kitchen Island · KCHN-01 moved into production — carcass milling started.
Tomáš Novak · 2 days ago
Production
AT
Rev C markups posted for the Dirty Kitchen · KCHN-05 — revision due Aug 8.
Atelier Team · 2 days ago
Revise
TN
Dining Room cabinets · CBT-01 passed in-house QC and were crated.
Tomáš Novak · 1 week ago
QC pass
TN
Submitted LNDR-01 Rev A shop drawings for review.
Tomáš Novak · 1 week ago
Submitted