MCG-2041 · Project overview

McGuinness Estate

A full custom residence at 3021 Del Rio Pike — millwork & furniture package for Shane & Michelle. Everything your Atelier Team is making, where it stands, and what needs you next.

In production 46 items · 35 millwork · 11 furniture Full custom residence 3 items awaiting you
Overall completion
38%
Design development and shop drawings are signed off across the estate; the palette is in final approval and the first pieces are on the production floor.
9
Delivered
14
In production
23
In design
In production
14
6 in QC this week
Pending approvals
3
1 past due · 2 open
Upcoming deliveries
2
Next Aug 14
Materials pending
5
Palette in final review

Milestones

Design development
Apr 22 · Signed
Shop drawings
Jun 03 · Approved
Materials & palette
In final review
Production start
Jun 18 · Underway
QC inspection
Sep 2026
Crating & freight
Oct 2026
On-site delivery
Nov 2026
Install complete
Dec 2026

Recent activity

AT
Kitchen Island · KCHN-01 moved into production.
Atelier Team · 2 days ago
Production
AT
Shop drawings for the Master WIC · WRD-01 approved.
Atelier Team · 4 days ago
Approved
AT
New palette samples posted for your review — white oak & honed marble.
Atelier Team · 5 days ago
Needs you
AT
Dining Room cabinets · CBT-01 passed QC and were crated.
Atelier Team · 1 week ago
QC pass
AT
Delivery window confirmed for the Wine Cabinets · CBT-03.
Atelier Team · 1 week ago
Scheduled

Jump into the project

Client view — all work attributed to the Atelier Team. No factory, supplier, or cost detail is shown.
McGuinness Estate · MCG-2041 · 3021 Del Rio Pike · 46 production items.